This is a parallel compliance track to MCS certification itself — you need both. For the certification and qualification side, see how to become a solar PV installer and what qualifications you need.
Why this is the installer's job, not the homeowner's
MIS 3002 is explicit: MCS Contractors "must follow the technical requirements and procedures" of EREC G98 or G99, and notification to the Distribution Network Operator "shall be undertaken by the MCS Contractor." This is a renewables-specific regulatory process that general electrical qualifications — 18th Edition, electrical NVQ Level 3 — simply don't cover, because it has nothing to do with domestic wiring regulations and everything to do with how generation connects to the public electricity network.
G98: the route most domestic installs use
National Grid Electricity Distribution's own guidance sets out G98 plainly: it covers "fully type tested installations under 16A per phase," installed on a "fit and notify" basis. In practice:
- You install and commission the system.
- You notify the DNO within 28 days of commissioning.
- The installation must meet specific technical conditions.
Those conditions, confirmed directly from National Grid's own page:
- Grid interface protection installed to local standards and functionally tested
- The system shuts down during a power outage
- An isolation switch capable of isolating all phases, lockable in the "off" position
- A circuit diagram displayed on site
- The installer hasn't commissioned any other generation in the same local geographic region within the preceding or following 28 days
That last condition is easy to miss and worth building into your scheduling — it's about managing the cumulative impact of multiple nearby connections on the local network, not just your individual job.

G99: when the simple route doesn't apply
G99 applies above the G98 threshold or to more complex connections. Unlike G98's fit-and-notify approach, G99 requires a formal application reviewed and accepted by the DNO before the system is energised. National Grid's own worked example shows how close to the line a typical domestic system can sit: a 4kW single-phase inverter divides by 230V to around 17.4A — just over the 16A G98 limit, pushing it into G99 territory.
For systems up to 50kW three-phase (or 17kW single-phase) that are fully type-tested and listed on the ENA's Type Test Verification Report Register, there's a simplified G99 route using a shorter form. Above that, or for non-type-tested equipment, the full application process applies, requiring location and site layout plans, manufacturer specification sheets, and generating unit data. Commissioning tests are the installer's own responsibility, and the DNO may require a witness test — which, National Grid's own guidance notes, carries a fee (though no DNO page we checked states a fixed figure for the application itself).
G100: a different kind of rule, running alongside G98/G99
G100 isn't a third size tier — it's a separate mechanism covering Customer Export Limitation Schemes, confirmed directly from National Grid's own page. Where a connection would otherwise need expensive network reinforcement to accommodate the generation or demand involved, a Customer Limitation Scheme lets you connect anyway by accepting an automatic cap: current is measured at the property's exit point and restricted to stay within the connection's capacity, acting within 15 seconds (and no later than 60 seconds) and failing safe if it can't. A system using a Customer Limitation Scheme still has to meet G98 or G99 for the generation equipment itself — G100 sits alongside that, not instead of it.
The aggregation rule: why "just" 16A isn't a fixed ceiling per job
This is the detail that catches people out. Ofgem's own decision on a 2026 Distribution Code change states plainly that generators are "permitted to connect and operate alongside other permanently wired Micro-generators provided the aggregate Registered Capacity of all Micro-generators in the Customer's Installation do not exceed G98's existing 16A per phase limit. Above this limit, Engineering Recommendation G99 requirements apply."
In plain terms: it's not just the new system you're installing that counts — it's everything already connected at that property added together. If a customer already has a 3kW G98 solar array and you're adding a 2kW extension, or a battery inverter that also exports, the combined capacity is what gets measured against the 16A line, not each device in isolation. Before any addition to an existing system, check what's already registered at the property.
What happens if you don't notify
We looked specifically for what happens when a generator isn't notified or compliance can't be confirmed. National Grid's own enforcement-process document sets out an escalating timeline under the Distribution Code's non-compliance process: written notices at weeks 0, 4, 8, 16 and 22, with a final consequence at week 26 — "If no evidence of compliance provided or evidence is not sufficient to demonstrate compliance with the Distribution Code, the DNO will make arrangements to de-energise the generation site's Connection Point." The document adds that derogations (exceptions) are "rarely granted."
To be precise about what we can and can't confirm: this is the general Distribution Code enforcement mechanism that would apply to an unnotified or non-compliant generator, not a penalty specifically written for "missing the 28-day window" in isolated terms. We didn't find an Ofgem statement using the phrase "breach of distribution licence conditions" for this specific scenario — treat that framing as a reasonable inference from the process above, not a direct quote. What's clear and confirmed: a DNO can and does move toward disconnecting an unresolved non-compliant connection, over a period of months, not days.
A genuinely new rule: plug-in solar
In August 2026, Ofgem approved a Distribution Code change (DCRP/MP/26/02) specifically creating a route within G98 for "Plug-in Micro-generators" — think balcony or plug-in solar kits, capped at 800W Registered Capacity. Two things worth knowing if this comes up in your work:
- These plug-in devices are limited to one per household, and stack with any existing wired generation against the same aggregate 16A threshold described above.
- Plug-in devices are exempted from several of the fixed-wire G98 requirements that apply to the systems you'll be installing — installer competency requirements, cut-out photographs, wiring/labelling/isolation requirements and loss-of-mains checks are all waived specifically for these consumer plug-in products, because the regulatory model for them is different (self-installed, consumer-facing).
Its actual implementation is tied to separate legislative changes (to the Plugs and Sockets and Electricity Safety regulations) coming into force, not automatic from the Ofgem decision date — worth checking current status if plug-in products become relevant to your work, since this area is still moving.
Common mistakes
- Treating MCS certification as covering grid connection too. It doesn't — G98/G99/G100 compliance is a separate process you're responsible for on every job.
- Assessing only the new system's capacity, not the aggregate. Adding to an existing installation can tip the combined total over the G98 threshold even if your addition alone wouldn't.
- Missing the 28-day G98 notification window. It's a hard deadline from commissioning, and non-compliance escalates toward disconnection over following months.
- Assuming G99's simplified route always applies. It only applies to type-tested equipment within specific capacity limits — anything else needs the full application process.
- Confusing G100 with a size threshold. It's an export/import limitation mechanism that can apply alongside either G98 or G99, not a third capacity tier.
Frequently asked questions
What's the actual difference between G98 and G99?
G98 covers installations under 16A per phase on a fit-and-notify basis — install first, then notify the DNO within 28 days. G99 covers larger or more complex connections and needs a formal application approved by the DNO before the system is energised.
Does a battery inverter count toward the G98 threshold?
The aggregate capacity of all generation and storage at a property is what's assessed against the 16A limit, per Ofgem's own confirmation — so yes, additional generation or export-capable storage at the same property counts toward the total, not just the newest device in isolation.
What is G100, and is it the same as G98/G99?
No — G100 governs Customer Export Limitation Schemes, a mechanism for connecting generation that would otherwise need network reinforcement, by accepting an automatic export/import cap. It can apply alongside G98 or G99 compliance for the generation equipment itself, not instead of it.
What happens if an installation is never notified to the DNO?
The Distribution Code's enforcement process escalates through written notices over several months, ending with the DNO arranging to de-energise the connection if compliance still can't be demonstrated by around 26 weeks. Exceptions are rarely granted.
Is there a fee for G98 or G99?
No DNO page we checked states an explicit notification fee for standard G98 or G99 applications. G99 can carry a discretionary witness-test fee if the DNO requires one, though no fixed figure is published.
How Nexis Academy can help
Nexis Academy is a City & Guilds Approved Centre (T91185) in Manchester. We currently deliver internal wall insulation training, with more trade and construction courses in development, including solar PV. We do not yet offer solar PV qualifications, so please register your interest to hear when that changes.
See also how to become a solar PV installer and what qualifications you need to install solar PV.
Sources
- MCS, MIS 3002: The Solar PV Installation Standard, v6.0, issued 18 March 2026 — installer's DNO notification responsibility.
- National Grid Electricity Distribution, "Micro generation (G98)" and "G99 connection procedures".
- National Grid Electricity Distribution, "Customer Export Limitation Schemes" (G100).
- Ofgem, decision to approve DCRP/MP/26/02, 11 August 2026 — aggregation rule, plug-in microgeneration route.
- National Grid, "Enforcement process for non-compliance with the Distribution Code".